A battery formation rack is an equipment system, while a saw supplier may only be asked to cut some of its aluminum frame members. The distinction matters in an RFQ: a drawing for an upright or cross rail does not authorize claims about cell contact, temperature control, electrical protection, or the completed rack. This guide turns an OEM’s released frame design into a checkable battery formation rack aluminum frame cutting request.
Featured image: a related energy-storage cabinet frame illustration from the existing JiurunCut media library. It is not a formation rack, a customer build, an approved configuration, or trial evidence.
Chroma’s formation system description distinguishes instrument and formation racks, describes trays, contacts and grippers, and identifies open-frame and cabinet designs. Those are examples of system interfaces, not Jiurun machine specifications. The OEM must define the actual rack architecture and acceptance criteria before a saw trial is meaningful.
State which parts are actually in the saw-cut kit
Start with the released assembly drawing and a member schedule. Give every rail, upright, brace and spacer its own part number and revision. For each part, specify the extrusion section and alloy/temper from the approved material drawing, quantity per rack, cut length and datum, end condition, and any visible-face requirement. Mark parts that will later be drilled, machined, fastened or coated by a different process. A saw cut is one operation in the chain; it does not create contact fixtures or certify a battery system.
Separate the cut list from purchased connectors, sheet-metal panels, trays, electrical hardware and thermal components. If a square or hollow section has an internal rib, send the real section drawing rather than a nominal outside size. Rib position can change where a part can be supported and clamped. The same nominal envelope can therefore require a different trial setup.

Define the rack interfaces before setting a length tolerance
A length number by itself does not tell the cutting team how the frame will assemble. Identify which rail ends locate a tray or shelf, which uprights set a deck spacing, and which members only support a cover. Show whether a part is measured to a square face, an angled face, a centerline or an assembly datum. State which faces must remain cosmetic and which can be hidden by a joint. The OEM should own the stack-up and decide the allowable variation at the assembly interface.
For each connection, specify whether the cut end bears against another member, stops short to leave clearance, or will be machined after cutting. A drawing revision that moves a connector or tray rail should trigger a cut-list review before another batch is released. Avoid replacing the OEM’s assembly tolerance with a machine brochure’s feed-repeatability figure: feeding repeatability and accepted finished-part length are different measures.

Give the saw supplier a trial that can fail clearly
Choose real sample stock from each distinct extrusion family, including the longest and shortest scheduled members and any thin-wall or asymmetric section. Provide the approved blade/end-finish expectation, the datum and inspection method, and the allowed burr or edge condition in the drawing. Ask the supplier to document the support and clamp arrangement, the first-part result, subsequent measured parts, and how offcuts are identified. If a finish or coating changes handling, include that stock condition in the trial.
Make acceptance conditional on the measured sample parts and the OEM’s fit check. A sample can satisfy a saw length inspection yet fail when joined to a tray rail or cover, so the OEM must inspect the relevant assembly interface. Conversely, a fit issue may come from a connector, drilling or the design stack-up rather than the cut. Keep those findings separate in the trial record.
The energy storage frame cutting overview discusses broader planning. For this formation-rack request, the useful next step is a member-by-member cut list and one released assembly interface. If the OEM still needs to resolve drawings, see the drawing-revision guide before quoting production quantities.
Keep the equipment and safety boundary explicit
Formation equipment can involve cell contacting, trays, thermal control and protective functions, as Chroma’s system description shows. A cutting-machine trial cannot verify those functions. The OEM or system integrator must approve the full rack design, electrical interfaces, ventilation or temperature strategy, guarding, and applicable site requirements. Jiurun’s scope in this article is evaluating whether supplied aluminum profiles can be cut into the specified frame blanks.
The video below shows a Jiurun aluminum-profile saw as general equipment context. It is not a formation rack, a trial of these profiles, proof of a particular machine configuration, or a performance guarantee.
RFQ information to send with the samples
- Released drawing package: rack assembly view, extrusion sections, part IDs, revision, quantities and measurement datums.
- Material state: alloy and temper, stock length, surface finish, straightness and any protected face called out by the OEM.
- End requirements: cut angle, acceptable length range, end-face and burr criteria, and any downstream machining allowance.
- Trial scope: representative member families, sample quantity, measuring tools, fit-check owner and the record needed before production release.
- Commercial boundary: who supplies stock, who makes holes and joints, who assembles the rack, and who approves the final battery equipment.
Ask for a quotation that names the actual profile families and sample plan. The saw model and tooling choice should follow the material, section and approved part criteria, not the word “battery” in the project title. A practical starting point is to send Jiurun the released cut list and sample profile drawings for a cutting-scope review. The OEM remains responsible for rack-system approval.
Questions buyers often ask
Can the saw supplier certify the formation rack?
No. A saw supplier can document cutting setup and measured sample blanks within the agreed scope. Formation contacts, electrical control, thermal design, safety functions and the complete rack require separate OEM or integrator validation.
Is one sample extrusion enough for all rack members?
Only if the released design and trial plan show that the sample represents the relevant sections and end conditions. Different walls, ribs, finishes and cut lengths can require different support or inspection decisions.
What should trigger a new cutting review?
A changed section, material state, joint datum, cut length, finish requirement, downstream allowance or assembly revision can invalidate an earlier sample conclusion. Compare the revised drawing and cut list before repeat production.